Scope of Work
The project, which involved geotechnical boreholes, was initiated in late May 2024 and is currently in progress. The work scope includes drilling 24 HQ3 cored boreholes, each between 10-15m deep combined total depth of 360m. The drilling rate was estimated at approximately 10m per shift, with a total of 36 shifts dedicated to drilling. Additionally, the project required a day for onsite permit/JHA/WRAC review, and two shifts for site establishment and pack up, bringing the total shifts to 48.